​In the afternoon of August 12, Vice Chairwoman of the PPC Dinh Thi Loan chaired a meeting with Central Power Corporation (EVNCPC) and related departments and agencies on the plan of the inauguration ceremony of Ly Son Electricity Project.

​Accordingly, the ceremony will be taken place on September 28, 2014 in Ly Son Island district with the present of Prime Minister Nguyen Tan Dung and nearly 400 delegates and thousands of Ly Son island’ residents (travel in vietnam)


In case of bad weather, the ceremony will be held in Binh Son district.

At the meeting, the Project’s schedule was also presented. Accordingly, the site clearance and compensation of overhead electric cable to Binh Son and Ly Son district completed, people in the Project area have handed over 100% of clean site for the investor. 100% of overhead electric cable was installed.

The project to connect Ly Son Island (vietnam travel)grid to the national power one through submarine cable was approved by the Ministry of Industry and Trade with the total investment capital of VND 652.5 billion, consisting of 28.7 kilometers of overhead electric cable and a 26.2km submarine cable, the project is planned to be completed and provides power in October 2014.

Leave a Reply

Subscribe to Posts | Subscribe to Comments

- Copyright © Vietnam classic tour - Skyblue - Powered by Blogger - Designed by Johanes Djogan -